The CPE team is beginning to plan a datacenter relocation, and we want to engage FESCO to be sure we plan and schedule this appropriately. The current time estimate is may-june, but we'd like help pinning it down to a specific 2 week window. We intend to attempt to minimize the disruption, but there will be impact in services. We'd like to request that FESCO provide a 2 week window within the may-june timeframe that is sufficiently 'safe' for us to target given release schedules.
To expand a bit, we don't expect everything to be down for 2 weeks, rather during that period there will be outages of various services as they are migrated and things like koji builder capacity and composes/updates pushes may be lower than normal. Once we determine this window a good deal of logistics and planning will happen, so once we do, it is likely pretty set in stone. Happy to expand further any questions we can answer at this point.
The current time estimate is may-june
what year?
The current time estimate is may-june what year?
Next year... 2020
F32 "Final Target date #1" is 2020-04-28. We usually don't slip much more than a week or two, but I think we should leave at least a month between that date and the downtime. So I'd say that FEdora POV is that any time in June is fine, with the first half of June being preferred.
(edited s/2019/2020/)
Metadata Update from @kevin: - Issue tagged with: meeting
[08:07:54] <nirik> #agreed window 1st to 15th june 2020 is approved. (+6,0,0)
Metadata Update from @kevin: - Issue close_status updated to: Accepted - Issue status updated to: Closed (was: Open)
Login to comment on this ticket.